Daniel K. Inouye Solar Telescope

...

1. Science/Technical Highlight (Anyone)

2. Photos (Anyone)

3. Directorate (Thomas and Dave)

3.1 Activities

3.2 Financial Status

  • DKIST operations carried forward approximately $28.16M in unencumbered funds into FY 2023 from previous years.  A total of $X.XXM in new funding has been obligated by NSF thus far in FY 2023 for a total of $YY.YYM.

  • Financial status of

    • DKIST operational expenditures for August 2023 were $Z.ZZM

    • Total YTD expenditures for DKIST operations are $XX.XXM.

    • The average DKIST spending for FY 2023 (burn rate; BR) is $Y.YYM/month.

4. Science Operations (Ali and Andres)

4.1 Cycle 2 Experiment Generation

...

  • Daily schedule during the OCP2.4 observing window ( - ):

    • Arrive at DSSC (carpools): 4:45am

    • Leaving DSSC: 5:00am

    • Arriving at site: 6:00am

    • Start Observatory Shutdown: 2:00pm

    • Leaving site: 2:30pm

    • Arrive at DSSC (end of day): 3:30pm

  • Science Operations schedules two Science Operations Specialists (SOS), and one Resident Scientist (RS) to support daily science operations at the summit.

5 Technical Operations (Heather and Paul)

5.1 Site & Facility Status

...

6 Instrumentation Operations (Bret, Friedrich, and Dave H.)

6.1 Optics

6.1.1 System Optics

  • M3 Spare coating samples were sent for ellipsometetric measurement along with a large batch of system optics (M2 through M10) for ongoing system coating model monitoring. Both the polarization system model and the flux budget will be updated accordingly. Additional cleaning information was collected from the vendor for testing on large samples coated along with the M3 Spare.

  • The DSSC custom lab metrology system light source upgrade verification continues. Additional measurements show high spectral resolving power at sensitivity levels of parts-per-million level (OD6) are achievable, in some wavelengths achieving 10 parts per billion noise floor (OD8). Filter design verification at levels of for instrument filters is an ongoing effort. An example comparing Cryo-NIRSP filter theory to delivered optics is below. NDSP6 is the 6-simultaneous-spectrograph DSSC lab metrology system.

    Image Added

6.1.2 Facility Instrument Distribution Optics (FIDO)

...

  • Some cold filters and samples have been sent for long wave IR throughput measurements to an outside vendor. Analysis of the DSSC data package on filter spatial transmission and blocking is ongoing.

  • A diffused, F/24 three-laser-wavelength alignment setup for MISI has been prototyped, and laser safety procedure discussions begun.

6.2.5 Cryogenic Near-Infrared Spectro-Polarimeter (Cryo-NIRSP)

...

6.9 Infrared Cameras

7 Data Center Operations (Bob and Alisdair)

7.1 Hardware Infrastructure

...