Daniel K. Inouye Solar Telescope

...

1. Science/Technical Highlight (Anyone)

2. Photos (Anyone)

3. Directorate (Thomas and Dave)

3.1 Activities

  • T. Rimmele participated in meetings with NSF during their visit Aug. 28 - Sept. 1. NSF staff included the Program Officer for NSO, C. Black,

3.2 Financial Status

  • DKIST operations carried forward approximately $28.16M in unencumbered funds into FY 2023 from previous years.  A total of $11.9M in new funding has been obligated by NSF thus far in FY 2023 for a total funding amount of $YY$40.YYM06M.

  • Financial status of

    • DKIST operational expenditures for August 2023 were $3.05M

    • Total YTD expenditures for DKIST operations are $26.30M.

    • The average DKIST spending for FY 2023 (burn rate; BR) is $2.39M / month.

4. Science Operations (Ali and Andres)

4.1 Status of Observing

  • The fourth observing window (OCP2.4) closed on .

  • The fifth observing window (OCP2.5) opened on (and will close on ).

  • was spent on ViSP external focus verification (on-sun activity, Instrumentation Group) and a Cryo-NIRSP straylight mitigation improvement (on-sun activity, Instrumentation Group).

...

4.5 Cycle Preparation

This should be maybe included. Not sure to what detail though.

4.6 Experiment Generation

...

4.8 Science Operations Tools

OpsTools (Proposal Architect work, Experiment Architect work, OPMT work, Loki work) updates/activities should be included here(?) (this is actually Bret or JohnH/HLS and Bob Tawa/OpsTools).

4.8.1 Management

Hiring process for new OpsTool software engineer, interviews scheduled. (Bob to fill in details).

5 Technical Operations (Heather and Paul)

5.1 Site & Facility Status

...

6 Instrumentation Operations (Bret, Friedrich, and Dave H.)

6.1 Optics

6.1.1 System Optics

...

6.9 Infrared Cameras

7 Data Center Operations (Bob and Alisdair)

7.1 Hardware Infrastructure

...