TechOps team
Accomplishments
Wrap up of 2024D Eng Period with
Shake and Bake of the Main movers and thermal systems prior to start of observing.
Sorting of surplus chemicals. paints etc for removal from site for safe and appropriate disposal.
M1 Co2 clean canceled due to humidity over threshold.
Optics covers removed.
Req for Thermal System Review placed - tentative dates on site are week of 11/4/2024
Chiller 1 repaired and back in service.
Vertiv (UPS service contractor) on site for repair and maintenance of large UPS systems.
InstOps team
Accomplishments
...