  • DKIST is in week 4 of Engineering period Eng. 2025a.

  • DKIST senior leadership has been preparing for the DKIST Concept of Operations review (see below)

Events

  • The AURA SOC meeting was held on Maui: 1/28 - 1/30

  • NSF Concept of Operations Review: 2/10 - 2/14

...

  • Preparation for ConOps review ongoing.

  • Scientists are creating the experiments for Cycle 3 accepted proposals.

  • Registered DKIST User database clean-up continues.

  • Planning of Cycle 4 is ongoing.

  • Preparation for a DKIST mini-workshop within the SDO 2025 Science Workshop - A Gathering of the Helio-Hive

TechOps team

Accomplishments

  • tbdPreparation for ConOps review ongoing.

InstOps team

Accomplishments

  • tbdPreparation for ConOps review ongoing.

Data Center team

Accomplishments

...

  • Preparation for ConOps review ongoing.

  • Drafted and finalized Strategy for polcals, groupcals, and trend data with stakeholders

  • Manually fixed and processed Cryonirsp runs with mislabeled exposure times

  • continued work on implementing a simpler status state machine in OPMT

  • Atttended and presented at the Cyber Infrsatructure (CI) Compass Virtual Workshop - “Data Management: From Instrument to First Storage”

EHS team

Accomplishments

  • Preparation for ConOps review ongoing.

  • Gary attended the NSF Research Infrastructure Office, Safety Officer Working Group at LIGO in Baton Rouge, LA.

    img_9647_720.jpg

  • We created a new “General Use Fall Protection” training for all DKIST employees that do not qualify as authorized users and do not work in fall protection equipment. It will cover walking working surfaces, recognizing fall hazards as well as proper ladder use.

  • The DKIST bi-mothly