Monthly Operations Report
Status as of Month DDJuly 31, YYYY2023
Table of Contents
Table of Contents | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
...
1. Science/Technical Highlight
A team of DKIST scientists and engineers traveled to the Leibniz-Institut für Sonnenphysik (KIS; previously known as the Kiepenheuer-Institut für Sonnenphysik) in Freiburg, Germany to help conduct the laboratory acceptance testing of the Visible Tunable Filter (VTF) instrument. The VTF will be the fifth facility-class instrument to be installed on DKIST, and it will be delivered by KIS as in-kind contribution in exchange for guaranteed time on the telescope for the German solar physics community. It successfully completed its laboratory acceptance testing in late July 2023 and is scheduled to be delivered and installed on DKIST in early 2024. The VTF has been under development for nearly a decade and is arguably the most highly anticipated DKIST instrument for the global solar physics community. For more information see:
2. Current Photos
3. Directorate
Dave Boboltz started his new position as DKIST Deputy Associate Director (DAD) on July 3, 2023.
Thomas and Dave worked on letters of support for KIS in Freiburg, Germany in response to recommendations from the Senate of the Leibniz Association.
Thomas traveled to KIS to attend the laboratory acceptance testing and to meet with KIS leadership regarding the KIS-DKIST partnership.
4. Science Operations (Alexandra and Andres)
...
4.2 Cycle observing progress
There were a total of XX experiments observed this month during Cycle Y.Z.
Otherwise, if there are no new observations to report this month we can just say so here and delete the table.
Cycle | Experiment ID | Observe Date | FIDO Configuration | Proposal Title |
---|---|---|---|---|
OCP2.X | MM/DD/YYYY | |||
4.3 Operations schedule and training activities
...
6.1 Facility Instrument Distribution Optics (FIDO)/Polarization Analysis and Calibration (PA&C)
Optics The optics team changed to FIDO config configuration 3a.
Final The final testing and delivery of beamsplitter GS50T950 was delayed due to delamination of the coating back in June. Coating was stripped and recoated by IOI, then resent to Zygo for final testing and assembly. During this period, the vendor discovered one pin for the cover was incorrectly installed, resulting in a unique cover for this optic. DKIST and the vendor agreed to clearly identify this one cover and associated optic.
Contract A contract for two additional beamsplitters was developed, including a quote from Zygo, coating development from IOI, associated statement of work, specifications, and executive summary. Package was delivered to AURA for approvals and submission to NSF.
New foam cutouts for stored FIDO optics were installed.
The GOS optics were cleaned to remove dust and bug parts.
Analysis An analysis of the GOS coolant flow shows no drop-off in coolant flow since the valve was fully opened in April. The team has decided not to agitate the valve this engineering period and will replace the valve in November.
Some work on the M9b table and mountings has begun, but is on hold due to higher priorities. The M9b blank is on order and expected toward the end of this year. Coating develop development for this blank continues.
6.2 Wavefront Correction System (WFS)
Further vibration data was were collected and analyzed. The Dampening the mount drive fans dampening has significantly improved performance. Other, lesser, vibration frequencies are now being investigated.
Testing of the non-common path vibration camera began with data taken in front of the ViSP slit. This These data is are under analysis.
New LUTs for rotational effects due to M3 and M6 have been calculated and deployed for the upcoming August OCP. These should significantly reduce the nutation effects seen by the Cryo-NIRSP.
...
6.7 Infrared Cameras
First Read-Only Integrated Circuit (ROIC) has been delivered. We are working on acceptable ITAR compliance.
Short wave detectors look acceptable and are on schedule. Mid-wave detectors will be inspected next.
An Operations Concept has been written so that we can begin exploring controllers for these detectors.
Schedule planning continues for lab development and future instrument integration.
Work on modifications to the DL-NIRSP and cryoCryo-NIRSP related to the IR cameras has been put on hold for higher priority tasks.
...
7.3.1 Calibration Pipelines
7.3.1 Data Released
There were a total of XX data sets released to their PIs this month and a total of YY data sets released to the public this month.
Otherwise, if there are no new data sets released this month we can just say so here and delete the table.
Experiment ID | Proposal Title | Observe Date | Release Date (PI) | Release Date (Public) |
---|---|---|---|---|
MM/DD/YYYY | MM/DD/YYYY | MM/DD/YYYY | ||
...