DKIST General

...

InstOps team

Accomplishments

  • In conjunction with the VTF team from Germany, completed the internal alignment of the single-etalon VTF. Began final alignment to the telescope but lost capability to use GOS light due to coolant flow issues. Cleaned up the Coudé in preparation for OCP 2.7.

  • Completed cooling and on-sun preparation for DL-NIRSP.

  • Initiated the pump-down and cooling of the Cryo-NIRSP after the MECO power outage in preparation for OCP 2.7.

  • Installed new heat dump system on the ViSP.

  • Worked with AURA on delivery of IR Camera SWIRs from Raytheon.

  • Worked on MCAO 11km DM design issues with AOA/Xinetics.

  • PCO determined issue with power-on failure of MCAO camera 1. PCO is working on intermittent failures of several other cameras.

  • Completed outstanding software release tasks and began final testing of High-Level Software (HLS) version Pono 7.

  • HLS supported cooling and power outages with monitoring, shutdown, and startup of computer systems.

...