Q1 Questions:

  • All: Given the holidays in December and expectations of vacations, what do we want to do in December, especially at the end of the month?

  • All: Are we going into an engineering period for the month of January?

  • InstOps: What is the Q4 plan for VTF? Will we have the KIS team out in November?

  • SciOps: What are the SolO and Parker windows we want to hit in Q4? Are there other co-observing opportunities?

  • SciOps:

  • TechOps: What is the longest non-concurrent PM/Upgrade we have this quarter?

  • InstOps/TechOps: Can the InstOps/TechOps tasks be accomplished concurrently in the November Engineering period?

Q1 Highest Priorities for each group:

  • Science Ops

  • Technical Ops

    • Jan-Feb:

      • Major Mech & Elec annual PMs (Mech Deferred to Apr-May Eng 2023B due to outages/weather)

      • Enclosure Azimuth reliability improvements & Testing

      • Thermal Systems Automation & Testing

      • M1 AP pump replace, convert off dynalene.

      • M1A cell internal leak repairs (Deferred to Apr-May Eng 2023B)

      • Optic Cleaning - tbc - M4 recommended. (deferred: M3/M5 maybe. M1 partial)

      • Assist VTF/Inst Grp per plan - cable trays, power, net. lieberts, thermocubes

    • Mar-Mid Apr:

      • S&B, Obs Support.

      • Training of more Duty Engineers

      • Work as can, compatible w On-Sun

    • End Apr:

      • Major Mech annual PMs - Encl, Mount, Coude

      • M1A cell internal leak repairs, Lateral Actuator Re-align

      • TBC eng. efforts as compatible w/ VTF install. “Quiet” time not broadly avail during normal shift due to overdue major PM.

  • Instrumentation Ops

    • Jan-Feb

      • VTF installation and alignment

      • Cryo-NIRSP Warm Filter Wheel Installation

      • Other instrument tasks as possible (unprioritized)

        • DL-NIRSP MISI-36 new mask install

        • DL-NIRSP Compressor swap

        • Potential other DL-NIRSP tasks based upon SAT results.

        • ViSP arm 1 camera swap

        • ViSP filter holders (new)

        • VBI-VTF Balor swaps

        • FIDO swap

    • Mar-Apr

      • DL-NIRSP MISI-36 Science Verification

      • VTF continued work (broadband imager?)

      • Vibration testing

        • On-sun/GOS Vibration testing (WFS, VBI, ViSP)

      • Other instrument tasks as possible (unprioritized)

        • On-sun/GOS Camera Tests (ViSP, VBI filter)

        • On-sun GOS Cryo-NIRSP modulator test/install

  • Data Center

    • Jan-March

      • Cryo-NIRSP

        • update Cryo pipeline and conduct review cycles until pipeline acceptance (Jan - Feb)

        • Run pipeline on backlog after acceptance

      • Quality Report Framework update (Jan - Feb)

        • update framework such that data is stored in machine readable format such that telemetry can be implented and trends found/highlighted

      • VISP Backlog

        • Complete Manual Processing Worker (MPW) (Jan)

        • Using MPW, process VISP backlog

      • Complete VISP Algorithm Change Proposal process (Jan -Mar)

        • update pipeline

      • Prep and submit Buy #6 HW buy

      • Complete/ implement reprocessing design changes

      • Process incoming cycle 2 data

    • April +

      • Process incoming data

      • reprocess VISP data after ACP-02 completion

    • Jan-Dec

      • develop and implement Cyber Security policies and controls

Group Priorities for Q1 (Schedule details to be worked out between the groups)

01-Jan202408-Jan15-Jan22-Jan29-Jan05-Feb12-Feb19-Feb26-Feb04-Mar11-Mar18-Mar25-Mar01-Apr08-Apr15-Apr22-Apr29-Apr06-May13-May20-May27-May03-Jun10-Jun17-Jun24-Jun01-Jul08-Jul15-Jul22-Jul29-JulTotal Solar EclipseFIDO reconfig VTF testsFIDO reconfig for OCP2.7S&B 3/11-3/12S&B 5/8-5/9FIDO config OCP 2.6M1/optics cleaning
Science Ops
Tech Ops
Instrumentation Ops
Data Center

Bar 2

Cycle 3 call preparation and release

Cycle 2.X / eclipse / SolO / PSP proposal prep

OCP2.7 observations

OCP2.6 / Eclipse / SolO / PSP observations 3/13 - 4/26 - 4/

Major PM items

Bearing Trucks

Regular PM

Regular PM

VTF installation

Cryo-NIRSP warm heads + other instrumentation tasks

On-Sun Instrument tests (e.g., MISI-36) 3/13 - 4/5

VTF assemb. IPL

VTF Install (GOS)

VTF GOS light required

Addl. Inst.

Cryo-NIRSP pipeline work

Complete Manual Processing Worker (MPW)

Complete Algorithm Change Proposal (ACP) process

Quality Report Framework update

Team

Members

On Maui

Sci Ops


Tech Ops


Inst Ops


Data Center