DKIST General

Operational Status

  • We are currently in week 3 of Science Operations period OCP 2.7.

Events

  • The Cycle 3 Proposal Call window closed ​on June 12, 2024, 23:00 GMT.

Personnel

SciOps and OpsTools team

Accomplishments

  • New Science Operations Specialist Francisco Salinas completed training with RH and Safety and he is now starting with the Science Operations training program.

  • Akamai intern Samantha Limon started working with Science Operations for 2 months. The project is called “Science Operations Specialist Group Daily Report Form Upgrade,” and the mentor is David Morris.

  • All Experiments for the FIDO 1a configuration were revised/updated and are now ready to be sent to the summit.

  • Significant Help Desk science support during the last week of the proposal submission window for Cycle 3.

  • Cycle 3 Technical Review tools preparation: the technical review committee uses the Jira framework to assign and track the progress during the process.

  • Ongoing observing support for OCP2.7.

TechOps team

Accomplishments

  • Completed significant number of concurrent (can complete in parrallel with observing) PM tasks that had been deferred from the engineering downtime.

  • Akamai Interns onboarding and welcome (first day on site 6/12/2023).

  • SPIE preparation (papers, presentations and posters)

  • M1 Co2 cleaning & cleaning in vicinity of optical systems - there have been multiple insect swarms on site over last couple of weeks.

  • Ongoing Observing support.

InstOps team

Accomplishments

Data Center team

Accomplishments

  • L2 data includes 2 profile FITS files alongside the L2 output data. These contain the “Original Profile” - roughly equivalent to the L1 frame, and the “Fit Profile”, which, if the inversion is successful, is very close to the original. Completed the Inclusion of 4 HDUs in the FITS output, 2xWavelength for the Original and Fit Profiles.

  • As part of a general DC stack update to Pydantic 2, completed the upgrade to Pydantic 2 in the REST api's - These had a higher priority being both forward facing and known vulnerable to a documented ReDOS attack vector.

  • Refactored the CRYO NIRSP SP solar gain task to perform fringe correction based on a parameter.

  • Monitored and fixed issues arising during proposal submission window.