/
2024 September 9 - 13

2024 September 9 - 13

2024-09-12 13.02.33.jpg DKIST General

Operational Status

  • DKIST is in week 1 of Engineering period 2024d. 

SciOps and OpsTools team

Accomplishments

  • Science Operations Specialists meeting to discuss OCP2.8 activities and problems. Defined action points in preparation for the next observing window.

  • Plan interviews for the Chief SOS hiring process.

  • Collaboration with Canada France Hawaii Telescope - Science Operations. Meeting to demonstrate how DKIST Science Operations manages documentation using Confluence.

TechOps team

Accomplishments

  • Annual Crane inspection completed - no major issues or discrepancies found.

  • MECO Large Account Manager visit and tour to discuss DKIST PV project, power usage, reliability and energy saving options.

  • Troubleshooting PA&C rack power issues and extraction of blown rack fan (1 of 3).

  • Coude Bearing Load Sensor (Condition monitoring system) permanent install complete (was started by Akamai intern) ready for Shake and Bake trial coming up.

  • CryoNIRSP He Compressors remote control interface hardware installation (ties into FMS for preemptive shutdown when coolant flow is lost).

  • PV Project bids received.

  • Critical Thermal System Pump Pm’s ongoing.

  • Enclosure & Mount Control Rack PM’s ongoing.

  • Coude Control Rack Cooling units removal fan mounting retrofit and replacement for Vibration Mitigation.2024-09-12 09.57.08.jpg 2024-09-12 09.57.08.jpg

 

2024-09-12 10.04.48.jpg
Building Cables for CryoNIRSP Compressor remote control. Photo by Paul Jeffers

 

2024-09-12 13.02.33.jpg
Coude Control Rack Fan Vibration Mitigation - Photo by Paul Jeffers

 

 

InstOps team

Accomplishments

  • Began engineering activities for Eng 2024D.

  • DL-NIRSP: upgraded and installed the slit mask stage, tested for light leaks, connected modulator stage to facility coolant.

  • Cryo-NIRSP: replaced context imager window O-ring, re-installed the context imager camera controller with new USB cable.

  • ViSP: Developed plans for November instrument upgrades and tests for vibration monitoring, modulator replacement, stray light baffles, and beam balancing. Added software upgrades to increase observing efficiency.

  • Changed the FIDO configuration for the OCP 2.9 observing configuration.

Data Center team

Accomplishments

  • Added support for multiple co-adds in DL-NIRSP data.

  • Completed a full rebuild of active documentation in Read-the-Docs

  • Improved the TileDataSet Class in the User tools for better interaction and user experience with VBI data

Related content