Electrical Power Distribution

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 20 Next »

Electrical Group Documents Folder

Enclosure Electrical Single Line Diagram

M3 As-built drawings folder

Electrical Single Line Drawing

Electrical Panel Schedules (Excel workbook)

Power Plan

Electrical System Interconnects (Excel workbook)

M1 and PA&C OSS Rack ePDU Outlet Assignments

Electrical Spare Parts

Electrical Utility Shutdown procedure

Floor Layouts


Quick and Dirty on Power Flavors / Outage expectations:

Standby power (S) - powered by generator after 30 second generator start/ATS transfer delay outage:

  • 300 KVA UPS

  • 10 KVA UPS for Utility building emergency lighting

  • 15 KVA UPS S&O emergency lighting

  • FTS AHU-02, Chiller CH-02, pumps CP-03 and CP-07 in UB

  • UB fans: generator room, mezzanine, tunnel

  • Tunnel sump pump

  • Generator day tank

  • Air compressor and dryer #2

  • Receiving and Coude cranes

  • M1 cart receptacle in receiving area

  • Elevator and LULA

  • PFlow and roll-up doors

  • Subset of S&O FTS pumps

  • Waste treatment aerator

  • Enclosure azimuth/shutter drives, vent gates, cranes

  • Coude instrument and OSS rack thermal/fans

Emergency power (EM) - 300 KVA Generator backed UPS. Continuously online
throughout power outages:

  • Fire alarm control panel

  • Network IDF racks: Utility building mezzanine and S&O ground,

mezz, utility level

  • Computer room row A

  • Control room wiremold outlets

  • Mount, Coude, Enclosure control systems and Enclosure Aperture drives

  • M1 cover

  • Xbox PLC/controls

  • GIS including GIC, TIM, LIC's with the exception of the OSS LIC

  • FMS PLCs/controls

  • Cryo-NIRSP electronics racks

UPS power (UPS) - 200 KVA UPS on normal power feed. Runtime spec of 5 minutes at full load. Actual runtime with current loading is much longer, however, if the UPS runs to an end-of-discharge shut down, it is prone to inrush circuit breaker tripping on re-start.

  • VBI, ViSP, DL-NIRSP, WFC, NCSP, VTF

  • 16C chillers

  • Computer room rows B, C, D

  • Instrument prep lab 3-phase 208V receptacles

  • M1/M2 OSS rack

  • PA&C OSS rack including M3 controller and OSS LIC

  • GOS blower rack

  • M3/M4/M6 thermal rack

  • M5/M6 control rack MER3 and M5 thermal rack MER2

Emergency lighting (UPSEM power) - Both the Utility building and S&O emergency lighting UPS's are fed from generator backed panels so emergency lighting remains powered for the duration of MECO outages.