2024 - Quarter 4

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this content. View the current version.

Compare with Current View Version History

« Previous Version 5 Next »

Q1 Questions:

  • All: Given the holidays in December and expectations of vacations, what do we want to do in December, especially at the end of the month?

  • All: Are we going into an engineering period for the month of January?

  • InstOps: What is the Q4 plan for VTF? Will we have the KIS team out in November?

  • SciOps: What are the SolO and Parker windows we want to hit in Q4? Are there other co-observing opportunities?

  • TechOps: What is the longest non-concurrent PM/Upgrade we have this quarter?

  • InstOps/TechOps: Can the InstOps/TechOps tasks be accomplished concurrently in the November Engineering period?

Q1 Highest Priorities for each group:

  • Science Ops

  • Technical Ops

  • Instrumentation Ops

  • Data Center

Group Priorities for Q1 (Schedule details to be worked out between the groups)

10-Jun202417-Jun24-Jun01-Jul08-Jul15-Jul22-Jul29-Jul05-Aug12-Aug19-Aug26-Aug02-Sep09-Sep16-Sep23-Sep30-Sep07-Oct14-Oct21-Oct28-Oct04-Nov11-Nov18-Nov25-Nov02-Dec09-Dec16-Dec23-Dec30-Dec06-Jan202513-Jan20-Jan27-Jan03-Feb10-Feb17-Feb24-FebS&B 7/29-7/30S&B 9/?-9/?
Overall
Science Ops
Tech Ops
Inst Ops
Data Center

OCP 2.7 5/27 - 7/9

Eng. 2024c 7/15-7/25

OCP 2.8 7/31 - 9/6

Engineering 2024d 9/9 - 9/?

OCP 2.9 9/? - 11/?

Engineering 2024e 11/? - 11/?

OCP 2.10? 11/? - 12/31

Engineering 2025a 1/2 - 1/31

Bar 2

Cycle 3 call preparation and release

Cycle 2.X / eclipse / SolO / PSP proposal prep

OCP 2.7 observing

OCP2.6 / Eclipse / SolO / PSP observations 3/13 - 4/26 - 4/

OCP 2.8 observing

Major PM items

Bearing Trucks

Regular PM

Non-concurrent PM

Non-concurrent PM

Concurrent PM & SciOps support

VTF installation

Cryo-NIRSP warm heads + other instrumentation tasks

On-Sun Instrument tests (e.g., MISI-36) 3/13 - 4/5

VTF assemb. IPL

VTF Install (GOS)

VTF GOS light required

Addl. Inst.

VTF 1-etalon on Sun????

VTF??

Cryo-NIRSP pipeline work

Complete Manual Processing Worker (MPW)

Complete Algorithm Change Proposal (ACP) process

Quality Report Framework update

Team

Members

On Maui

Sci Ops


Tech Ops


Inst Ops


Data Center