DKIST General

Operational Status

  • DKIST is in week 1 of science observing period OCP 2.9 

Events

Personnel

  •  

SciOps and OpsTools team

Accomplishments

TechOps team

Accomplishments

  • Wrap up of 2024D Eng Period with

  • Shake and Bake of the Main movers and thermal systems prior to start of observing.

  • Sorting of surplus chemicals. paints etc for removal from site for safe and appropriate disposal.

  • M1 Co2 clean canceled due to humidity over threshold.

  • Optics covers removed.

  • Req for Thermal System Review placed - tentative dates on site are week of 11/4/2024

  • Chiller 1 repaired and back in service.

  • Vertiv (UPS service contractor) on site for repair and maintenance of large UPS systems.

2024-09-24 14.32.38.jpg

InstOps team

Accomplishments

Data Center team

Accomplishments

 

  • No labels