Daniel K. Inouye Solar Telescope

...

1. Science/Technical Highlight (Anyone)

2. Photos (Anyone)

3. Directorate (Dave)

3.1 Activities

  • For the month of June, DKIST continued weeks 2-6 of OCP2.7 science observing.

  • The DKIST Directorate prepared for and presented to the NSF’s 2-year extension proposal review held June 4-6, 2024.

...

  • DKIST operations carried forward approximately $13.82M in unencumbered funds into FY 2024 from previous years.  A total of $14.00M in new funding has been obligated by NSF thus far in FY 2024.

  • Financial status of

    • DKIST operational expenditures for the current month were $2.47M

    • Total YTD expenditures for DKIST operations are $17.64M.

    • Total outstanding encumbrances are $10.61M.

    • The average DKIST spending for the past 12 months (burn rate; BR) is $2.51M / month.

image-20240626-162707.png

4. Science Operations (Ali and Andres)

4.1 Status of Observing

4.1.1 Regular Cycle Observing

...

5 Technical Operations (Paul)

5.1

...

Site & Facility Status

5.

...

2 General Site & Facility Repairs, Improvements & Upgrades

...

Vestibule Design and Fabrication/Construction solicitation

...

...

Reviewed 50% design package for elevator vent redesign

  • Corresponding with M3 on any questions they may have regarding the elevator vent louvers. Need to take more pictures when time and techs are available.

  • Completed Kick-Off meeting with M3 for elevator vent redesign. Sent out the precast sealant and elevator submittals.

...

Power outage support/recovery; Restarted Regular, Generator, and UPS, communication, and thermal systems.

...

Chiller 02 urgent troubleshooting, leak in system 2 resulted in lost refrigerant charge

  • JCI fixed cracked tee in System 2 discharge line and recharged refrigerant

  • RFQ for service contract, vendor rep visit onsite.

...

Chiller 05/06 PM and troubleshooting visit

  • Both chillers wer tuned, topped off, inspected

  • Found a facility flow switch misbehaving

  • Both circuits on CH06 were low, circuit 2 had a leak at the pressure relief valve connection

...

5.3 Electrical/Electronics/PLC and Facility Management System

5.3.1  Highlights of Recurring Preventative Maintenance Performed in October

...

6 Instrumentation Operations (Bret, Friedrich, and Dave H.)

6.1 Optics

6.1.1 System Optics

...

  • .

7 Data Center Operations (Bob and Alisdair)

7.1 Hardware Infrastructure

...