  • DKIST went through Shake & Bake 8/5 - 8/6 in preparation for OCP 2.8.

  • Start of the first week of OCP 2.8.

Events

  • DKIST staff and DKIST Ambassadors attended the Big Bear Solar Observatory (BBSO) Summer School 7/29 - 8/2. Several DKIST staff members presented at the Summer School.

  • Visit to DKIST by the NOIRLab Head of Engineering and one other engineers Services and Head of Systems Engineering - 8/13

  • Visit to DKIST by a Rubin AIV manager - 8/12

image-20240809-173510.pngImage Added

Personnel

  • The seven Akamai interns working at DKIST finished up their internships this week. See the NSO blog post here.

SciOps and OpsTools team

Accomplishments

...