Q4 Questions:

  • All: Given the holidays in December and expectations of vacations, what do we want to do in December, especially at the end of the month?

    • We discussed this at the June 13 meeting. Where we landed is December is engineering. I left a gap for the week of Christmas/New Year’s assuming most staff on vacation.

  • All: Are we going into an engineering period for the month of January?

    • SciOps has planned to go back on sun only in February for Cycle 3 observing. We are not prepared to be ready in January.

  • InstOps:

    • What is the Q4 plan for VTF? Will we have the KIS team out in November?

      • Possibly. VTF work in November would be completion of Etalon 1 installation (no Etalon 2 work). KIS will need to determine their status on Etalon 2 work in Freiburg before deciding whether to come to Maui in November. Next meeting to discuss in July.

  • SciOps:

    • What are the SolO and Parker windows we want to hit in Q4? Are there other co-observing opportunities?

      • No there are no other. Supporting SO and PSP is enough additional work.

  • TechOps: What is the longest non-concurrent PM/Upgrade we have this quarter?

  • InstOps/TechOps:

    • Can the InstOps/TechOps tasks be accomplished concurrently in the November Engineering period?

Q4 Highest Priorities for each group:

  • Science Ops

    • May need to discuss extension for Sunrise co-observing.

    • PSPE21 on 9/30. This is a Cryo-NIRSP observation only.

    • October 1: Solar Orbiter co-observing: R_BOTH_HRES_HCAD_Filament_Prominence - high-resolution observations of prominence at West limb, close to Earth quadrature (~4hrs) - pVSTP - FOR DKIST: on-disk filament observation SOOP Coordinators: T. Kucera, S. Parenti

    • October 2 - 19: different co-observing programs: AR Long Term (multiple days - may not be consecutive), SMALL_MRES_MCAD_Earth-Quadrature - high-resolution observations of target at West limb, close to Earth quadrature (~2hrs) - pVSTP SOOP Coordinator: P. Chitta, SMALL_HRES_HCAD_RS-burst 30 mins of EUI super high cadence observations - pVSTP Moved to 19 October during DKIST-available time (1800-2200 hrs, depending on when best fits the SPICE observations for Fast Wind).

    • Need to continue with FIDO 3a AND 3c experiments. Configuration for Solar Orbiter should be 3c - need for FIDO changes of CL2a position - hot swap testing FIDO-150.

    • Support on two saturdays instead of sundays.

    • Other science operations priorities:

      • Experiment generation for Cycle 3 start: ideally we need to know at that point what DL modes to include.

      • Cycle 4 Proposal Call preparation in full swing.

      • Testing of Cycle 4 configurations? We did not want to offer untested configurations anymore.

      • Rolling shutter for ViSP: increase of operational efficiency (no more NDs) and increased frame rate at same exposure time at the cost of lower SNRs and exposure time testing starting from scratch.

      • DL-NIRSP SV with Cycle 2 experiments continued → visible camera needs to be implemented, focused (float?) → required for Cycle 4 preparation, need to know what to offer.

      • Testing of 50/50 and 70/30 BS.

      • ViSP modulator replacement: beam wobble mitigation.

      • Step one in prep for ViSP beam attenuators: put the mounts in.

  • Technical Ops

    • OCP2.9

      • surplus material disposal and Haz material storage org and inventory

      • baseyard packing of plate coil boxes into Containers and reorg of baseyard.

      • Site EV Charger (x2) installation.

      • Main UPS servicing & repair (S&B and first day of ops ) - small risk to obs.

      • ongoing con-current maintenance.

    • Eng 2024E (& 2025A)

      • VTF support etech/ mtech / ME & EE.

      • Removal (and replacement) of the Enclosure Cable Wrap Hoses for TMW and HW. 3 to 4 weeks of non movement on the enclosure. Can be broken into parts ie one hose at a time.

      • Annual Electrical Distribution System Panel Maintenance - site wide electrical outage approx 4 days provisional plan Wed 1/8 to Sat 1/11 with Sun 1/12 as contingency and system restart on Mon 1/13.

      • Upgrade of PESDs for voltage absence and voltage presence detection on main system drive disconnects.

      • UB Electrical Tie-In for Solar Panels - site outage for 2 days.

      • Enclosure Az Drive tuning with Siemens Tech on site - 1 week

      • CDU server Room switch over for Row A & B ???? - 3 to 4 weeks no cooling - unlikely.

      • Coude LIC Refurbish - 2 weeks with no motion & permanent estop.

  • Instrumentation Ops

    • InstOps needs two/three weeks to warm Cryo-NIRSP, open to install new resolvers, and cool down.

      • Plan was for 2025/Q1 (January), assuming there is 3 weeks of engineering

      • Other CN work: leak checks, cold-head duty cycle, new slit masks, broken filter holders, 2nd grating base, replacement of grating harmonic drive.

    • InstOps would like to install MCAO 4km DM table and M9b table.

      • Arrival of tables by November will be possible but challenging. January would be ok but would overcommit InstOps for work this month (working along with CN, MISI-116).

      • This keeps the MCAO and M9b work on schedule for initial frame installation in winter 2025/26.

      • Would require crane, opening of floor, realignment of M9a onto new table.

    • Potential MISI-116 installation

      • November not possible, January may be possible.

      • Still lots of smaller parts to be built, including several moving mechanisms.

      • Next opportunity for installation may be winter 2025/26.

    • Numerous smaller tasks to be done in either Nov or Jan engineering period

      • ViSP filter holders. ViSP beam-balancing optics and testing.

      • More GOS cover work, depending upon repairs in July and Sep.

      • Optics as-built metrology.

      • DL-NIRSP modulator cooling.

      • Potential removal and shipment of VTF cameras for single-gain upgrade.

      • Discuss possibility for further vibration campaign work during winter shutdown.

    • HLS

      • Upgrade to Java 17. Extensively test all instruments and systems by executing observations.

      • Install and test tgz data accumulation for Data Center Globus transport.

      • Upgrade login security.

      • Potentially move engineering data storage services to Amazon Web Services

  • Data Center

    • Finish Cryo-NIRSP pipeline acceptance and begin Processing Cryo-NIRSP backlog

    • Finish DL-NIRSP Beta Pipeline and begin acceptance cycle(s)

    • Move all quicklook movies to Vimeo - For Back-up and bandwidth savings

    • Upgrade the Ceph cluster to the “Pacific” revision

    • OT - Implement Globus Accounting changes

    • OT - Design Experiment Architect templating solution

Group Priorities for Q4 (Schedule details to be worked out between the groups)

Roadmap Planner
maplinks
timelinetrue
source%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222024-09-15%2000%3A00%3A00%22%2C%22endDate%22%3A%222025-01-31%2000%3A00%3A00%22%2C%22displayOption%22%3A%22WEEK%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Overall%22%2C%22color%22%3A%7B%22lane%22%3A%22%23f15c75%22%2C%22bar%22%3A%22%23f15c75%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-05-29%2006%3A21%3A35%22%2C%22id%22%3A%2272f45c5a-be3f-4234-8bdc-23447bf57a6f%22%2C%22title%22%3A%22OCP%202.7%205%2F27%20-%207%2F9%22%2C%22description%22%3A%22%22%2C%22duration%22%3A6.614862495049506%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-07-22%2005%3A11%3A53%22%2C%22id%22%3A%22c42912b0-d516-42e5-980f-e3cae12d6202%22%2C%22title%22%3A%22Eng.%202024c%207%2F22-8%2F2%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9712783366336633%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-08-05%2023%3A17%3A13%22%2C%22id%22%3A%227499a403-f8c0-445b-b3d2-a8ccd820074a%22%2C%22title%22%3A%22OCP%202.8%208%2F7%20-%209%2F6%22%2C%22description%22%3A%22%22%2C%22duration%22%3A4.76340704950495%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-09-09%2003%3A32%3A04%22%2C%22id%22%3A%225c98ee2c-b356-4502-b58a-eabe5a35e754%22%2C%22title%22%3A%22Eng.%202024d%209%2F9%20-%209%2F20%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.000931801980198%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-09-23%2023%3A17%3A13%22%2C%22id%22%3A%22b38e5af0-eedc-487e-9ca3-4748b0141939%22%2C%22title%22%3A%22OCP%202.9%209%2F25%20-%2011%2F10%22%2C%22description%22%3A%22%22%2C%22duration%22%3A6.832733782178218%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-12-08%2003%3A02%3A22%22%2C%22id%22%3A%22dfcad96c-b5b9-4b7c-b32b-19bd82dba3d0%22%2C%22title%22%3A%22Engineering%202024f%2011%2F%3F%20-%2011%2F%3F%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9812486336633663%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222025-01-05%2003%3A02%3A22%22%2C%22id%22%3A%221949f724-83a3-428d-b67b-4131eb6fc10c%22%2C%22title%22%3A%22Engineering%202025a%201%2F2%20-%201%2F31%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.892001108910891%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-11-24%2003%3A02%3A22%22%2C%22id%22%3A%2272f2f00e-14d2-4d86-8b5c-121a48021a71%22%2C%22title%22%3A%22InstOps%202024e%20on%20Sun%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.0207832871287126%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222025-02-02%2000%3A49%3A19%22%2C%22id%22%3A%227e4d13b2-0eff-48c0-b60c-c0ebdfb9dac2%22%2C%22title%22%3A%22OCP%203.0%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.9415951683168315%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-11-10%2008%3A57%3A34%22%2C%22id%22%3A%22f35aefb3-1363-44dd-9528-ba59723ed699%22%2C%22title%22%3A%22Eng.%202024e%2011%2F11-11%2F22%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9812486336633663%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222024-12-22%2003%3A12%3A36%22%2C%22id%22%3A%2278cac08d-fb9b-4644-aabe-1c85e27aee00%22%2C%22title%22%3A%22Low-intensity%20Mintenance%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9416248712871287%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Science%20Ops%22%2C%22color%22%3A%7B%22lane%22%3A%22%23f6c342%22%2C%22bar%22%3A%22%23fadb8e%22%2C%22text%22%3A%22%23594300%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22title%22%3A%22Bar%202%22%2C%22description%22%3A%22This%20is%20the%20second%20bar.%22%2C%22startDate%22%3A%222023-08-01%2000%3A00%3A00%22%2C%22duration%22%3A4.428571428571429%2C%22rowIndex%22%3A0%2C%22id%22%3A%22d33c42f8-d31a-49eb-9803-84e511d1ed3e%22%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-01-01%2001%3A39%3A48%22%2C%22id%22%3A%22c032419d-8c39-434d-ad46-089887214369%22%2C%22title%22%3A%22Cycle%203%20call%20preparation%20and%20release%22%2C%22description%22%3A%22Cycle%203%20call%20preparation%20and%20release%22%2C%22duration%22%3A11.96039603960396%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-01-01%2001%3A39%3A48%22%2C%22id%22%3A%225fd1026b-798e-4e83-980e-5f0eb984595d%22%2C%22title%22%3A%22Cycle%202.X%20%2F%20eclipse%20%2F%20SolO%20%2F%20PSP%20proposal%20prep%22%2C%22description%22%3A%22%22%2C%22duration%22%3A9.970297029702971%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-05-29%2002%3A26%3A22%22%2C%22id%22%3A%220d96296b-eb64-43a4-a35b-e81246d54edd%22%2C%22title%22%3A%22OCP%202.7%20observing%22%2C%22description%22%3A%22%22%2C%22duration%22%3A6.6544763564356435%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-03-12%2021%3A54%3A39%22%2C%22id%22%3A%22b1517f13-c9f4-4453-9fe5-607900f48acc%22%2C%22title%22%3A%22OCP2.6%20%2F%20Eclipse%20%2F%20SolO%20%2F%20PSP%20observations%203%2F13%20-%204%2F26%20-%204%2F%22%2C%22description%22%3A%22%22%2C%22duration%22%3A6.717623762376237%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-07-29%2021%3A37%3A25%22%2C%22id%22%3A%22fd550dee-99f3-4b5b-bbb7-2d68d5543ed0%22%2C%22title%22%3A%22OCP%202.8%20observing%22%2C%22description%22%3A%22%22%2C%22duration%22%3A5.7732783366336635%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-09-29%2019%3A56%3A54%22%2C%22id%22%3A%22472d25e0-f7e9-4e96-8ca6-0daf2a87731d%22%2C%22title%22%3A%22PSP%20SolO%20co-obs%209%2F31-10%2F19%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.674228831683168%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Tech%20Ops%22%2C%22color%22%3A%7B%22lane%22%3A%22%233b7fc4%22%2C%22bar%22%3A%22%236c9fd3%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-01-01%2001%3A39%3A48%22%2C%22id%22%3A%220eb30015-4539-4f4e-a892-84a4a3cbed58%22%2C%22title%22%3A%22Major%20PM%20items%22%2C%22description%22%3A%22%22%2C%22duration%22%3A8.98019801980198%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-03-03%2022%3A20%3A11%22%2C%22id%22%3A%22517ae858-2fc5-4f40-9a88-62c6be2715e3%22%2C%22title%22%3A%22Bearing%20Trucks%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222024-04-29%2018%3A01%3A48%22%2C%22id%22%3A%2277051969-75a9-4a8f-b780-fc5f09e750db%22%2C%22title%22%3A%22Regular%20PM%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.9256237623762376%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-07-15%2000%3A56%3A08%22%2C%22id%22%3A%2247e31c32-d47a-44a2-898a-d2273d9f001e%22%2C%22title%22%3A%22Non-concurrent%20PM%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.991129821782178%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-09-08%2019%3A12%3A12%22%2C%22id%22%3A%2245e13323-4ab1-46b0-8433-88456d4fbb09%22%2C%22title%22%3A%22Non-concurrent%20PM%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.010902099009901%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-05-29%2003%3A33%3A51%22%2C%22id%22%3A%22cf53d2a9-7431-4c8f-ba74-040367ac7070%22%2C%22title%22%3A%22Concurrent%20PM%20%26%20SciOps%20support%22%2C%22description%22%3A%22%22%2C%22duration%22%3A6.664367445544555%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-11-10%2009%3A53%3A12%22%2C%22id%22%3A%22d74717a8-07f5-45bc-92f6-935fe304dd34%22%2C%22title%22%3A%22Non-concurrent%20PM%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9613971485148516%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-12-08%2017%3A29%3A24%22%2C%22id%22%3A%22022babdb-a910-4ad5-a42c-41c27c6387c8%22%2C%22title%22%3A%22Non-concurrent%20PM%20and%20Major%20Upgrades%22%2C%22description%22%3A%22%22%2C%22duration%22%3A7.892100118811881%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Inst%20Ops%22%2C%22color%22%3A%7B%22lane%22%3A%22%23d04437%22%2C%22bar%22%3A%22%23dc7369%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-01-08%2009%3A58%3A48%22%2C%22id%22%3A%22aa1854ed-8d1e-4dae-9b82-5511d16323dc%22%2C%22title%22%3A%22VTF%20installation%22%2C%22description%22%3A%22%22%2C%22duration%22%3A7.945386138613862%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222023-12-30%2011%3A24%3A21%22%2C%22id%22%3A%227234b279-883b-438b-a56c-5e235d2b53d8%22%2C%22title%22%3A%22Cryo-NIRSP%20warm%20heads%20%2B%20other%20instrumentation%20tasks%22%2C%22description%22%3A%22%22%2C%22duration%22%3A9.198019801980198%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-03-13%2003%3A19%3A00%22%2C%22id%22%3A%22316132b4-ce6a-48b2-a895-474800d4fc3c%22%2C%22title%22%3A%22On-Sun%20Instrument%20tests%20(e.g.%2C%20MISI-36)%203%2F13%20-%204%2F5%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.668049504950495%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-04-29%2010%3A06%3A10%22%2C%22id%22%3A%2206a4fdac-1d9b-465f-8943-47afa7ef37f7%22%2C%22title%22%3A%22VTF%20assemb.%20IPL%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.0048346534653465%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222024-05-06%2000%3A50%3A21%22%2C%22id%22%3A%22f4aac571-1e56-4099-ba5a-a4c52ca90c6f%22%2C%22title%22%3A%22VTF%20Install%20(GOS)%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9702970297029703%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222024-02-19%2004%3A59%3A24%22%2C%22id%22%3A%22196c2356-f1e3-4f8e-8b1f-bc7152950b3d%22%2C%22title%22%3A%22VTF%20GOS%20light%20required%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222024-05-19%2022%3A44%3A27%22%2C%22id%22%3A%22abbee585-bc6e-46e2-9a27-e65c28e23f81%22%2C%22title%22%3A%22Addl.%20Inst.%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-11-10%2008%3A57%3A14%22%2C%22id%22%3A%226296ebc7-9109-485d-85d7-a92326e3a913%22%2C%22title%22%3A%22VTF%20tasks%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.991040712871287%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-11-25%2007%3A31%3A40%22%2C%22id%22%3A%22b853f4e9-74b2-46fd-830a-805949586885%22%2C%22title%22%3A%22ViSP%20testing%20on%20Sun%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9713674455445545%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222024-07-14%2021%3A36%3A42%22%2C%22id%22%3A%226a82852b-ad4d-480b-a283-c365fe2392b1%22%2C%22title%22%3A%22DL-NIRSP%20(4%20tasks)%2C%20Cryo%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.010902099009901%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-11-25%2007%3A19%3A00%22%2C%22id%22%3A%22a6a9944d-f867-4dbf-b4c6-304f7439c198%22%2C%22title%22%3A%22VTF%20on%20Sun%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9416248712871287%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-11-10%2008%3A13%3A13%22%2C%22id%22%3A%227de54d0e-2c87-4745-b8a4-c44512eaf064%22%2C%22title%22%3A%22ViSP%20tasks%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.999981306930693%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Data%20Center%22%2C%22color%22%3A%7B%22lane%22%3A%22%238eb021%22%2C%22bar%22%3A%22%23aac459%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A5%2C%22startDate%22%3A%222024-01-01%2001%3A39%3A48%22%2C%22id%22%3A%2255361029-d966-4fb6-b549-76cceb5171b1%22%2C%22title%22%3A%22Cryo-NIRSP%20pipeline%20work%22%2C%22description%22%3A%22%22%2C%22duration%22%3A12.96039603960396%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-01-01%2001%3A39%3A48%22%2C%22id%22%3A%227c55337d-d6a6-4ced-966e-e478bb1a8850%22%2C%22title%22%3A%22Complete%20Manual%20Processing%20Worker%20(MPW)%22%2C%22description%22%3A%22%22%2C%22duration%22%3A4.514851485148514%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A7%2C%22startDate%22%3A%222024-01-01%2001%3A39%3A48%22%2C%22id%22%3A%2299c25c11-0e8e-488a-9def-36212f692647%22%2C%22title%22%3A%22Complete%20Algorithm%20Change%20Proposal%20(ACP)%20process%22%2C%22description%22%3A%22%22%2C%22duration%22%3A12.96039603960396%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-01-01%2001%3A39%3A48%22%2C%22id%22%3A%22c1edd33d-8e1f-4d10-ad46-3aa9701a8548%22%2C%22title%22%3A%22Quality%20Report%20Framework%20update%22%2C%22description%22%3A%22%22%2C%22duration%22%3A8.970297029702971%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-06-10%2001%3A02%3A22%22%2C%22id%22%3A%2252f1a9ab-70e1-49ae-8b1d-d706b1a772ce%22%2C%22title%22%3A%22Cryo-NIRP%20Acceptance%22%2C%22description%22%3A%22Cryo-NIRP%20Acceptance%22%2C%22duration%22%3A4.972574257425743%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222024-06-10%2001%3A02%3A22%22%2C%22id%22%3A%228eb11925-f9c5-4111-b4a0-28236c4925ed%22%2C%22title%22%3A%22DL-NIRSP%20Beta%22%2C%22description%22%3A%22%22%2C%22duration%22%3A5.54691089108911%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222024-06-10%2001%3A02%3A22%22%2C%22id%22%3A%22ccd159b0-cdaa-4ec3-add9-3a17e39d14f4%22%2C%22title%22%3A%22Movies%20to%20Vimeo%22%2C%22description%22%3A%22%22%2C%22duration%22%3A4.447940594059406%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A5%2C%22startDate%22%3A%222024-08-29%2008%3A52%3A52%22%2C%22id%22%3A%22088f8454-0eda-427d-b7ae-fea0de9f3a3c%22%2C%22title%22%3A%22Upgrade%20Ceph%20%20to%20Quincy%22%2C%22description%22%3A%22%22%2C%22duration%22%3A6.061782178217822%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A6%2C%22startDate%22%3A%222024-07-07%2015%3A40%3A59%22%2C%22id%22%3A%22188e60ab-bd3e-4c66-95a1-5e3089ef33b8%22%2C%22title%22%3A%22Experiment%20Architect%20Templating%20Design%22%2C%22description%22%3A%22%22%2C%22duration%22%3A8.01219801980198%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A7%2C%22startDate%22%3A%222024-06-17%2005%3A34%3A52%22%2C%22id%22%3A%229dc5ca75-05c2-4271-be50-05b57d5daf53%22%2C%22title%22%3A%22Globus%20Accounting%20changes%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.022158415841584%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222024-07-18%2013%3A52%3A16%22%2C%22id%22%3A%22e6742f06-b1f7-48a7-a676-1d0869ff22f9%22%2C%22title%22%3A%22DL%20NIRSP%20acceptance%22%2C%22description%22%3A%22%22%2C%22duration%22%3A11.457722772277227%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-07-15%2002%3A04%3A33%22%2C%22id%22%3A%2232a6c85f-0085-4186-9fa5-47496b96d61a%22%2C%22title%22%3A%22Cryo-NIRSP%20data%20processing%20and%20publication%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.952792079207921%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Marker%201%22%2C%22markerDate%22%3A%222023-08-15%2000%3A00%3A00%22%7D%2C%7B%22markerDate%22%3A%222023-10-01%2022%3A20%3A11%22%2C%22title%22%3A%22Q4%202023%20start%22%7D%2C%7B%22markerDate%22%3A%222024-04-08%2012%3A37%3A03%22%2C%22title%22%3A%22Total%20Solar%20Eclipse%22%7D%2C%7B%22markerDate%22%3A%222024-04-29%2014%3A16%3A51%22%2C%22title%22%3A%22FIDO%20reconfig%20VTF%20tests%22%7D%2C%7B%22markerDate%22%3A%222024-05-29%2000%3A13%3A44%22%2C%22title%22%3A%22FIDO%20reconfig%20for%20OCP2.7%22%7D%2C%7B%22markerDate%22%3A%222024-03-11%2005%3A57%3A50%22%2C%22title%22%3A%22S%26B%203%2F11-3%2F12%22%7D%2C%7B%22markerDate%22%3A%222024-05-27%2023%3A16%3A32%22%2C%22title%22%3A%22S%26B%205%2F8-5%2F9%22%7D%2C%7B%22markerDate%22%3A%222024-03-12%2020%3A13%3A17%22%2C%22title%22%3A%22FIDO%20config%20OCP%202.6%22%7D%2C%7B%22markerDate%22%3A%222024-05-07%2018%3A31%3A55%22%2C%22title%22%3A%22M1%2Foptics%20cleaning%22%7D%2C%7B%22markerDate%22%3A%222024-08-05%2008%3A18%3A50%22%2C%22title%22%3A%22S%26B%208%2F5%20-8%2F6%22%7D%2C%7B%22markerDate%22%3A%222024-09-23%2008%3A19%3A01%22%2C%22title%22%3A%22S%26B%209%2F23-9%2F24%22%7D%2C%7B%22markerDate%22%3A%222024-10-21%2003%3A19%3A36%22%2C%22title%22%3A%22FIDO%20reconfig%20%3F%3F%3F%22%7D%2C%7B%22markerDate%22%3A%222024-11-24%2019%3A39%3A53%22%2C%22title%22%3A%22S%26B%2011%2F25-11%2F26%22%7D%5D%7D
pagelinks
titleRoadmap%20Planner
hashc0ccc3f1b0b6a502fbc2fc94006bfa0564128d2be5397833b8bded3896decdad

Q4 Shift Pattern

https://docs.google.com/spreadsheets/d/1-wIzUsrqRgWFCiHZQ6PL32nPj1EDdg0a1mwuZdVYr9Y/edit?gid=391699390#gid=391699390