DKIST is in week 4 of science observing period OCP 2.9
DKIST was down for a brief period 10/15 - 10/16 due to a tree branch falling on the MECO power lines to the summit.
Events
The DKIST Acting AD will be meeting with NSF - 10/25
Personnel
Multiple postings for positions in Technical Operations open on Maui.
SciOps and OpsTools team
Accomplishments
...
Updated inventory and portal systems such that small datasets (< 1 GB) do not show up on the portal as 0 GB.
The DL team had reported that the demodulation matrices vary by a small but significant-enough amount spatially within each IFU group. As a result the DC Fit demodulation matrices for all spatial pixels in DLNIRSP pipeline
Reimplement VBI in the Processing Preparation Worker to include IP execution IDs in order to address the reason that some VBI processing runs were failing
completed the remaining updates to he applications services to pydantic 2. this effort is now complete and all services have been updated.
EHS team
Accomplishments
Prepared and submitted the bi-monthly Safety and Health report.