Worked on the DKIST Concept of Operations plan.
Start of Annual Electrical Panel Maintenance where does not interrupt Eng work.
Enclosure Shutter Testing with migrated code.
Enclosure cable wrap hose surgical removal with prejudice and start of new hose installation.
Aperture plate system valve disassembly / rebuild and system refill and test.
InstOps team
Accomplishments
Worked on the DKIST Concept of Operations plan.
Completed coude installation of the MCAO DM tables and M9b/M9a table.
Completed metrology on coude optical systems.
Completed review of IR Camera thermal analysis and latest mechanical design iteration.
Continued work on MCAO 11km options for manufacture.
Closed out all VTF Nov/Dec 2024 campaign tickets.
...