2024 December 16 - 20

2024 December 16 - 20

DKIST General

  • DKIST submitted the NSF-requested Concept of Operations plan December 18, 2024. An external review of the plan will take place on Maui the week of February 10, 2025.

Operational Status

  • DKIST is in week 2 of Engineering period Eng 2024f.

Personnel

  • The DKIST team has multiple job postings for positions on Maui.

SciOps and OpsTools team

Accomplishments

  • Continued work on Cycle 2 closing activities in collaboration with the Data Center team and the VBI team.

  • Cycle 3 Experiment generation (ongoing).

TechOps team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

  • Start of Annual Electrical Panel Maintenance where does not interrupt Eng work.

  • Enclosure Shutter Testing with migrated code.

  • Enclosure cable wrap hose surgical removal with prejudice and start of new hose installation.

  • Aperture plate system valve disassembly / rebuild and system refill and test.

 

  • 2024-12-18 10.48.31.jpg
    Enclosure Panel Maintenance - Photo by PFJ

     

     

    2024-12-18 10.47.21.jpg
    Hose surgical removal - photo by PFJ

     

     

     

  •  

     

     

InstOps team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

  • Completed coude installation of the MCAO DM tables and M9b/M9a table.

 

 

  • Completed metrology on coudé optical systems.

  • Completed review of IR Camera thermal analysis and latest mechanical design iteration.

  • Continued work on MCAO 11km options for manufacture.

  • Closed out all VTF Nov/Dec 2024 campaign tickets.

Data Center team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

EHS team

Accomplishments

Related content