  • Worked on the DKIST Concept of Operations plan.

  • Start of Annual Electrical Panel Maintenance where does not interrupt Eng work.

  • Enclosure Shutter Testing with migrated code.

  • Enclosure cable wrap hose surgical removal with prejudice and start of new hose installation.

  • Aperture plate system valve disassembly / rebuild and system refill and test.

  • 2024-12-18 10.48.31.jpgImage Added

    2024-12-18 10.47.21.jpgImage Added

    2024-12-12 09.32.36.jpgImage Added

  • 2024-12-19 14.55.16.jpgImage Added

    IMG_2864.jpgImage Added

InstOps team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

  • Completed coude installation of the MCAO DM tables and M9b/M9a table.

2024-12-12 11.49.22.jpgImage Added

  • Completed metrology on coudé optical systems.

  • Completed review of IR Camera thermal analysis and latest mechanical design iteration.

  • Continued work on MCAO 11km options for manufacture.

  • Closed out all VTF Nov/Dec 2024 campaign tickets.

Data Center team

Accomplishments

...

  • Worked on the DKIST Concept of Operations plan.

  • Submitted the DKIST Monthly Site Safety report for November 2024.

  • Fall protection training was completed by summit crews.

  • Maui Fire Dept. gave us hands on Fire Extinguisher training utilizing a fun digital simulator.

  • The EHS team had their first onboarding meeting with our new safety management application, Sospes. We looking to start to roll out Mid-January.

  • Completed the install of the new choking rescue devices from LifeVac on the summit and the DSSC.