2024 - Quarter 4

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this content. View the current version.

Compare with Current View Version History

« Previous Version 30 Next »

Q4 Questions:

  • All: Given the holidays in December and expectations of vacations, what do we want to do in December, especially at the end of the month?

    • We discussed this at the June 13 meeting. Where we landed is December is engineering. I left a gap for the week of Christmas/New Year’s assuming most staff on vacation.

  • All: Are we going into an engineering period for the month of January?

    • SciOps has planned to go back on sun only in February for Cycle 3 observing. We are not prepared to be ready in January.

  • InstOps:

    • What is the Q4 plan for VTF? Will we have the KIS team out in November?

      • Possibly. VTF work in November would be completion of Etalon 1 installation (no Etalon 2 work). KIS will need to determine their status on Etalon 2 work in Freiburg before deciding whether to come to Maui in November. Next meeting to discuss in July.

  • SciOps:

    • What are the SolO and Parker windows we want to hit in Q4? Are there other co-observing opportunities?

      • No there are no other. Supporting SO and PSP is enough additional work.

  • TechOps: What is the longest non-concurrent PM/Upgrade we have this quarter?

  • InstOps/TechOps:

    • Can the InstOps/TechOps tasks be accomplished concurrently in the November Engineering period?

Q4 Highest Priorities for each group:

  • Science Ops

    • May need to discuss extension for Sunrise co-observing.

    • PSPE21 on 9/30. This is a Cryo-NIRSP observation only.

    • October 1: Solar Orbiter co-observing: R_BOTH_HRES_HCAD_Filament_Prominence - high-resolution observations of prominence at West limb, close to Earth quadrature (~4hrs) - pVSTP - FOR DKIST: on-disk filament observation SOOP Coordinators: T. Kucera, S. Parenti

    • October 2 - 19: different co-observing programs: AR Long Term (multiple days - may not be consecutive), SMALL_MRES_MCAD_Earth-Quadrature - high-resolution observations of target at West limb, close to Earth quadrature (~2hrs) - pVSTP SOOP Coordinator: P. Chitta, SMALL_HRES_HCAD_RS-burst 30 mins of EUI super high cadence observations - pVSTP Moved to 19 October during DKIST-available time (1800-2200 hrs, depending on when best fits the SPICE observations for Fast Wind).

    • Need to continue with FIDO 3a AND 3c experiments. Configuration for Solar Orbiter should be 3c - need for FIDO changes of CL2a position - hot swap testing FIDO-150.

    • Support on two saturdays instead of sundays.

    • Other science operations priorities:

      • Experiment generation for Cycle 3 start: ideally we need to know at that point what DL modes to include.

      • Cycle 4 Proposal Call preparation in full swing.

      • Testing of Cycle 4 configurations? We did not want to offer untested configurations anymore.

      • Rolling shutter for ViSP: increase of operational efficiency (no more NDs) and increased frame rate at same exposure time at the cost of lower SNRs and exposure time testing starting from scratch.

      • DL-NIRSP SV with Cycle 2 experiments continued → visible camera needs to be implemented, focused (float?) → required for Cycle 4 preparation, need to know what to offer.

      • Testing of 50/50 and 70/30 BS.

      • ViSP modulator replacement: beam wobble mitigation.

      • Step one in prep for ViSP beam attenuators: put the mounts in.

  • Technical Ops

    • OCP2.9

      • surplus material disposal and Haz material storage org and inventory

      • baseyard packing of plate coil boxes into Containers and reorg of baseyard.

      • Site EV Charger (x2) installation.

      • Main UPS servicing & repair (S&B and first day of ops ) - small risk to obs.

      • ongoing con-current maintenance.

    • Eng 2024E (& 2025A)

      • VTF support etech/ mtech / ME & EE.

      • Removal (and replacement) of the Enclosure Cable Wrap Hoses for TMW and HW. 3 to 4 weeks of non movement on the enclosure. Can be broken into parts ie one hose at a time.

      • Annual Electrical Distribution System Panel Maintenance - site wide electrical outage approx 4 days provisional plan Wed 1/8 to Sat 1/11 with Sun 1/12 as contingency and system restart on Mon 1/13.

      • Upgrade of PESDs for voltage absence and voltage presence detection on main system drive disconnects.

      • UB Electrical Tie-In for Solar Panels - site outage for 2 days.

      • Enclosure Az Drive tuning with Siemens Tech on site - 1 week

      • CDU server Room switch over for Row A & B ???? - 3 to 4 weeks no cooling - unlikely.

  • Instrumentation Ops

    • InstOps needs two/three weeks to warm Cryo-NIRSP, open to install new resolvers, and cool down.

      • Plan was for 2025/Q1 (January), assuming there is 3 weeks of engineering

      • Other CN work: leak checks, cold-head duty cycle, new slit masks, broken filter holders, 2nd grating base, replacement of grating harmonic drive.

    • InstOps would like to install MCAO 4km DM table and M9b table.

      • Arrival of tables by November will be possible but challenging. January would be ok but would overcommit InstOps for work this month (working along with CN, MISI-116).

      • This keeps the MCAO and M9b work on schedule for initial frame installation in winter 2025/26.

      • Would require crane, opening of floor, realignment of M9a onto new table.

    • Potential MISI-116 installation

      • November not possible, January may be possible.

      • Still lots of smaller parts to be built, including several moving mechanisms.

      • Next opportunity for installation may be winter 2025/26.

    • Numerous smaller tasks to be done in either Nov or Jan engineering period

      • ViSP filter holders. ViSP beam-balancing optics and testing.

      • More GOS cover work, depending upon repairs in July and Sep.

      • Optics as-built metrology.

      • DL-NIRSP modulator cooling.

      • Potential removal and shipment of VTF cameras for single-gain upgrade.

      • Discuss possibility for further vibration campaign work during winter shutdown.

    • HLS

      • Upgrade to Java 17. Extensively test all instruments and systems by executing observations.

      • Install and test tgz data accumulation for Data Center Globus transport.

      • Upgrade login security.

      • Potentially move engineering data storage services to Amazon Web Services

  • Data Center

    • Finish Cryo-NIRSP pipeline acceptance and begin Processing Cryo-NIRSP backlog

    • Finish DL-NIRSP Beta Pipeline and begin acceptance cycle(s)

    • Move all quicklook movies to Vimeo - For Back-up and bandwidth savings

    • Upgrade the Ceph cluster to the “Pacific” revision

    • OT - Implement Globus Accounting changes

    • OT - Design Experiment Architect templating solution

Group Priorities for Q4 (Schedule details to be worked out between the groups)

09-Sep202416-Sep23-Sep30-Sep07-Oct14-Oct21-Oct28-Oct04-Nov11-Nov18-Nov25-Nov02-Dec09-Dec16-Dec23-Dec30-Dec06-Jan202513-Jan20-Jan27-JanS&B 9/23-9/24FIDO reconfig ???S&B 11/25-11/26
Overall
Science Ops
Tech Ops
Inst Ops
Data Center

OCP 2.7 5/27 - 7/9

Eng. 2024c 7/22-8/2

OCP 2.8 8/7 - 9/6

Eng. 2024d 9/9 - 9/20

OCP 2.9 9/25 - 11/10

Engineering 2024f 11/? - 11/?

Engineering 2025a 1/2 - 1/31

InstOps 2024e on Sun

OCP 3.0

Eng. 2024e 11/11-11/22

Low-intensity Mintenance

Bar 2

Cycle 3 call preparation and release

Cycle 2.X / eclipse / SolO / PSP proposal prep

OCP 2.7 observing

OCP2.6 / Eclipse / SolO / PSP observations 3/13 - 4/26 - 4/

OCP 2.8 observing

PSP SolO co-obs 9/31-10/19

Major PM items

Bearing Trucks

Regular PM

Non-concurrent PM

Non-concurrent PM

Concurrent PM & SciOps support

Non-concurrent PM

Non-concurrent PM and Major Upgrades

VTF installation

Cryo-NIRSP warm heads + other instrumentation tasks

On-Sun Instrument tests (e.g., MISI-36) 3/13 - 4/5

VTF assemb. IPL

VTF Install (GOS)

VTF GOS light required

Addl. Inst.

VTF tasks

ViSP testing on Sun

DL-NIRSP (4 tasks), Cryo

VTF on Sun

ViSP tasks

Cryo-NIRSP pipeline work

Complete Manual Processing Worker (MPW)

Complete Algorithm Change Proposal (ACP) process

Quality Report Framework update

Cryo-NIRP Acceptance

DL-NIRSP Beta

Movies to Vimeo

Upgrade Ceph to Quincy

Experiment Architect Templating Design

Globus Accounting changes

DL NIRSP acceptance

Cryo-NIRSP data processing and publication

Q4 Shift Pattern