DKIST General
Operational Status
We are currently in week 5 of Science Operations period OCP 2.7.
Events
Personnel
SciOps and OpsTools team
Accomplishments
The Technical Review of submitted Cycle 3 Proposals and the preparations for the respective Science Review are in full swing.
A welcome email to all Cycle 3 Proposers has been sent including information about the proposal review timeline.
Ongoing observing support for OCP2.7.
Continued on-standby for Sunrise III co-observing (daily until launch).
Draft plan for OCP2.8.
TechOps team
Accomplishments
Ongoing observing support for OCP 2.7.
InstOps team
Accomplishments
Working on issues with Cryo-NIRSP context imager controller.
Continued lab integration of MCAO mechanical components into frame.
Continued development of M9b upgrade, including optical table order and concept mount design.
Ongoing observing support for OCP 2.7.
Data Center team
Accomplishments