DKIST General
Operational Status
DKIST is in week 4 of engineering period 2024e
Events
The AURA Board meeting was held Dec. 3-4 in Washington DC. The NSO Director and DKIST Acting Associate Director attended.
Personnel
SciOps and OpsTools team
Accomplishments
The Cycle 3 Experiment Generation process officially started on December 02. Ten NSO scientists are on a mission to create, review, and test the experiments for Cycle 3. The plan is to have all the experiments available for summit execution before the end of February 2025.
Release the SOS Daily Report form (V3) with some improvements to log Operations activities during observing days.
TechOps team
Accomplishments
InstOps team
Accomplishments
Data Center team
Accomplishments
EHS team
Accomplishments
Prepared and submitted the bi-monthly DKIST Safety and Health report.