2024 November 4 - 8

DKIST General

Operational Status

  • DKIST is in week 7 of science observing period OCP 2.9 

Personnel

  • Congratulations to Gary Candido for his promotion to DKIST EHS Manager!

  • Congratulations to David Morris on his promotion to Chief Science Operations Specialist!

SciOps and OpsTools team

Accomplishments

  • Experiment Architect tool release. Congratulations and thank you to the OpsTools team.

TechOps team

Accomplishments

  • .Prep for the upcoming engineering period with VTF support, EMCS part code migration & test, TAC piping continuation to Coude Inst racks.

  • Paul attended ConOps planning meeting in Boulder & Stephanie remote.

  • Site interview being planned for one Snr ME candidate, Phone interviews coordinating for MTech Super, etech assc & Industrial Cleaner.

  • CMMS Admin opening posted.

InstOps team

Accomplishments

  • Support for OCP 2.9

  • Preparation for VTF team arrival.

  • Shipping of MCAO and M9b tables. Preparation for shipping of associated table legs.

  • Diagnostic work on WFS actuator board failures.

  • Report on results of Oct 30th FIDO swap.

  • Worked on enhanced cost estimate justifications for Instrumentation Development SFR and 2-year CA extension proposal at the request of AURA/NSF.

Data Center team

Accomplishments

  • Added support for arbitrary X/Y loop order in DL-NIRSP Processing. The DC up till now assumed that the mosaic loop ordering is:

    X_step: Y_step:

    but in reality it can be any order. The DC needs to support both because the assumption of loop order is integral to how we parse aborts and figure out the shape of the completed mosaic.

  • Included processing candidate id in the failure ticket summary for ingesting a locked processing candidate. Failure ticket summaries previously specified the conversation id. The processing candidate id was needed and and now serves to distinguish the tickets in the Jira dashboard.

  • Created a dataset-inventory mask that allows incorrect values to be overridden. The DC encounters 2 types of errors in dataset-inventory. 

    • Ones that occur because of a problem/change  to a calculation, which the DC has to date fixed (the calculation) and regenerated the inventory, . 

    • Ones that occur because the header values that go into the calculation are wrong. 

This fix aimed at giving the DC a tool for all of the cases where a regeneration of inventory will not solve the problem while preserving the ability to regenerate dataset inventory to solve the first kind of problem.

EHS team

Accomplishments