DKIST General
Operational Status
We are currently in week 1 of Science Operations period OCP 2.7.
Events
Personnel
SciOps and OpsTools team
Accomplishments
TechOps team
Accomplishments
M1 and Feed Optics Snow / Nitrogen cleaning prior to start of observing.
Mount, Enclosure, Coude and Thermal Shake and Bake complete coming out of engineering period 2024B and start of OCP2.7 (5/24).
SOS control of Facility Thermal mode switching from housekeeping to observing mode via FCS interface.
Review and start of the FAA laydown area final demobilization of material & containers.
invading bug (biological) removed from GOS Air Force target.
InstOps team
Accomplishments
Data Center team
Accomplishments