DKIST General
Operational Status
We are currently in week 4 of Science Operations period OCP 2.7.
Events
SPIE meeting Yokohama, Japan - 6/16-6/21
Personnel
SciOps and OpsTools team
Accomplishments
Cycle 3 Proposal Call submission windows closed successfully. Congrats to the scientist supporting the Help Desk for an excellent job.
Cycle 3 Proposal material was handed over to the Chairs of the Technical Review Committee (TRC) and the Science Review Committee (SRC).
Cycle 3 Technical Review started with Lucas Tarr as the chair of the Technical Review Committee.
Ongoing observing support for OCP2.7.
On standby for Sunrise III co-observing (daily until launch).
TechOps team
Accomplishments
Attending, Presenting Papers and Posters and Chairing Sessions at SPIE Yokohama.
Testing of the Enclosure Altitude Encoder & data analysis.
Ongoing observing support for OCP 2.7.
InstOps team
Accomplishments
Ongoing discussion regarding IR camera sensors and controllers.
Continued optical work on FIDO gray beamsplitter,
HLS has worked on upgrading the data transfer rate to Boulder.
Ongoing observing support for OCP 2.7.
Data Center team
Accomplishments