DKIST General

Operational Status

  • DKIST is going through Shake & Bake 8/5 - 8/6 in preparation for OCP 2.8.

  • Start of the first week of OCP 2.8.

Events

  • Visit to DKIST by two NOIRLab engineers - 8/13

  • Visit to DKIST by a Rubin AIV manager - 8/12

SciOps and OpsTools team

Accomplishments

  • The SciOps team has contacted the Cycle 3 Time Allocation Committee (TAC) Chair to coordinate dates for the TAC meeting.

  • OCP 2.8 started 8/7 with flare patrol experiments being prioritized. Below is a screenshot of one of the pointing targets for the flare patrol.

  • Cycle 3 PI’s will be contacted next week with an update about the progress made regarding the proposal review process. 

  • The SciOps team continues to work on SciOps Jira tickets and preparing for Cycle 3 Experiment Generation.

image.png

TechOps team

Accomplishments

  • The TechOps and InstOps teams worked together to perform the DKIST Shake & Bake 8/5 - 8/6 in preparation for handover to Science Operations.

InstOps team

Accomplishments

Data Center team

Accomplishments

  •  Created a pre-commit hook to check workflow names against corresponding .rst documentation files.

  • Corrected SP and CI spatial WCS information for Level 1 Cryo-NIRSP data

  • Updated DL-NIRSP canonical data to use MISI data