2024 December 16 - 20

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this content. View the current version.

Compare with Current View Version History

« Previous Version 3 Next »

DKIST General

  • DKIST submitted the NSF-requested Concept of Operations plan December 18, 2024. An external review of the plan will take place on Maui the week of February 10, 2025.

Operational Status

  • DKIST is in week 2 of Engineering period Eng 2024f.

Personnel

  • The DKIST team has multiple job postings for positions on Maui.

SciOps and OpsTools team

Accomplishments

  • Continued work on Cycle 2 closing activities in collaboration with the Data Center team and the VBI team.

  • Cycle 3 Experiment generation (ongoing).

TechOps team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

InstOps team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

  • Completed coude installation of the MCAO DM tables and M9b/M9a table.

  • Completed metrology on coude optical systems.

  • Completed review of IR Camera thermal analysis and latest mechanical design iteration.

  • Continued work on MCAO 11km options for manufacture.

  • Closed out all VTF Nov/Dec 2024 campaign tickets.

Data Center team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

EHS team

Accomplishments

  • Worked on the DKIST Concept of Operations plan.

  • Submitted the DKIST Monthly Site Safety report for November 2024.

  • Completed the install of the new choking rescue devices from LifeVac on the summit and the DSSC.