GIS CIDL
Global Interlock System Configuration Item Data List
Document | Title | Rev. | Date |
---|---|---|---|
SPEC-0046 | GIS Specification | A | 25-Oct-12 |
SPEC-0112 | GIS Architecture | C | 26-Jan-15 |
SPEC-0141 | GIS Operational Concept Definition | A | 25-Oct-12 |
SPEC-0140 | GIS Functional Description | C | 26-Jan-12 |
SPEC-0117 | GIS Global Tag Names |
| 25-Oct-12 |
|
|
|
|
PROC-0013 | GIS Project Plan | B | 25-Feb-15 |
CMX-0003 | GIS Compliance Matrix | A | 1-Nov-12 |
|
|
|
|
ICD 1.1-4.5 | Telescope Mount Assembly to Global Interlock System | C | 7-Feb-13 |
ICD 1.2-4.5 | M1 Assembly to Global Interlock System | A | 22-Mar-10 |
ICD 1.3-4.5 | TEOA to Global Interlock System | B | 26-Jul-12 |
ICD 1.5-4.5 | Feed Optics to Global Interlock System | Draft | Oct-08 |
ICD 2.1-4.5 | Wave Front Control-Coudé to Global Interlock System | Draft | 26-Oct-12 |
ICD 3.0-4.5 | Instruments to Global Interlock System | A | 26-Oct-12 |
ICD 3.1.1-4.5 | Polarimetry Analysis and Calibration to Global Interlock System | A | 30-Jan-13 |
ICD 3.1.2-4.5 | Master Clock and Synchro Network to Global Interlock System | Draft | 26-Oct-12 |
ICD 3.1.3-4.5 | Coudé Station to Global Interlock System | Draft | 26-Oct-12 |
ICD 3.1.5-4.5 | Coudé Environmental Systems to Global Interlock System | Draft | 26-Oct-12 |
ICD 3.2-4.5 | Visible Broadband Imager to Global Interlock System | Draft | 26-Oct-12 |
ICD 3.3-4.5 | Visible Spectro-polarimeter to Global Interlock System | Draft | 26-Oct-12 |
ICD 3.4.1-4.5 | Diffraction Limited Near-IR Spectropolarimeter to Global Interlock System | A | 2-Oct-12 |
ICD 3.4.2-4.5 | Cryogenic Near-IR Spectropolarimeter to Global Interlock System | A | 2-Oct-12 |
ICD 3.5-4.5 | Visible Tunable Filter to Global Interlock System | A | 2-Oct-12 |
ICD 3.6-4.5 | Camera Systems to Global Interlock System | A | 2-Oct-12 |
ICD 4.2-4.5 | Observatory Control System to Global Interlock System | A | 17-Oct-12 |
ICD 4.5-5.0 | Global Interlock System to Enclosure | D | Mar-13 |
ICD 4.5-6.0 | Global Interlock System to Support Facility and Buildings | A | 27-Jul-12 |
ICD 4.5-6.3 | Global Interlock System to Facility Equipnent | Draft | 30-Aug-06 |
ICD 4.5-6.7 | Global Interlock System to Facility Thermal Systems | A | 13-Apr-10 |
SPEC-0063 | Interconnects and Services | C | 2-Feb-12 |
|
|
|
|
SAF-0002 | GIS Hazard Analysis | A | 18-Oct-12 |
RPT-0047 | GIS Reliability and Availability Analysis | A | 25-Oct-12 |
RPT-0048 | Power and Heat Dissipation Budget | A | 29-Oct-12 |
RPT-0050 | GIS IAB Report | A | 25-Oct-12 |
RPT-0057 | GIS FAT Report | A | 25-Feb-15 |
|
|
|
|
SPEC-0079 | Approved Parts | B |
|
|
|
|
|
MAN-0001 | GIS Operations Manual | A | 26-Jan-15 |
|
|
|
|
TN-0157 | GIS GuardLogix Programming | A | 26-Mar-13 |
|
|
|
|
DWG-0065 | GIS Configuration | B | 25-Oct-12 |
|
|
|
|