DKIST General
Operational Status
DKIST is in week 1 of Engineering period Eng. 2025b.
Events
NSF Concept of Operations (ConOps) review was held on Maui: 2/10 - 2/14
The 2025 SDO Science Workshop “A Gathering of the Helio-Hive” was held this week in Boulder with NSO/DKIST participation.
On 2/21 a mini-workshop on DKIST Data Retrieval and Analysis was held within the SDO workshop.
SciOps and OpsTools team
Accomplishments
The Science Operations Manager and the Program Scientist for Operations both presented at the DKIST ConOps review.
DKIST Scientists are finishing the experiments required for OCP3.1 starting the first week of March.
A New Jira project was created to track the execution of Cycle 3 experiments during the year.
TechOps team
Accomplishments
The TechOps Manger and the TechOps Systems Engineer both presented at the DKIST ConOps review.
Instrumentation team
Accomplishments
The Instrumentation Program Manager and the Instrumentation Program Scientist both presented at the DKIST ConOps review.
Continued instrument preparations for upcoming on-sun campaign.
Completed report on successful M7 optical alignment effort.
Completed report on ghost and stray light testing of ViSP.
Data Center team
Accomplishments
The Data Center Manager and the Data Scientist both presented at the DKIST ConOps review.
Data Center Scientist is presenting the DKIST User Tools at the SDO workshop.
EHS team
Accomplishments
The EHS Manager presented at the DKIST ConOps review
The DKIST bi-monthly health and safety report was submitted 2/12
Gary attended ASSP Program Fall Protection Administrator training.
High Level Software team
Accomplishments
Design and installation planning for the Durham Profiler
Database performance improvements tested
Automated observatory open and close scripts updated and tested