/
2024 July 29-August2

2024 July 29-August2

DKIST General

Operational Status

  • DKIST is in the second week of Engineering Period 2024c 7/24 - 8/2.

  • There was a brief power outage at the summit on Monday, July 29.

Events

  •  

Personnel

  • Welcome Dr. Paolo Turri a new DKIST scientist working on adaptive optics who started on July 29.

SciOps and OpsTools team

Accomplishments

  • The SciOps Daily Report form was updated with new features, and it is ready for the next OCP.

  • Technical Review of Cycle 3 proposals continues with good progress.

TechOps team

Accomplishments

  • TAC automation Testing conducted during Cryo-NIRSP Cooling restart.

  • Further set of Power interrupts on Mon Jul 29th evening - required full thermal restart on Tue Jul 30th.

  • Quarterly Goal review meetings ongoing.

  • Leak repairs at Service Level Racks complete

  • Repaired CCC rack HeX leaked again and removed - unit not reliably repairable due to location of leak - alternate options being explored.

  • Road Closed again due to Public Interference delaying container removal from FAA area.

  • Fire alarm system (Enclosure) fixed and fully operational.

  • Congrats to Brialyn & Sebastien for SPIE Best Paper Award in the Ground-based and Airborne Telescope X conference - Paper title : An update on the DKIST’s sitewide vibration surveillance and mitigation efforts

 

2024-07-24 11.30.56.jpg
Service Ring Rack Cooling Leak Repair (Photo by Paul Jeffers)

 

 

 

InstOps team

Accomplishments

  • Met with Raytheon RTX on the continuation of the contract for delivery of short-wave IR sensors and future production of mid-wave IR sensors.

  • Restarted all instrumentation.

  • Tested Cryo-NIRSP context imager controller issue.

  • Performed GOS testing of DL focus and alignment.

  • Tested deployment of HLS Pono 8 release.

  • Repaired GOS occulter controller.

Data Center team

Accomplishments

  •  Began writing on the DKIST DC Cybersecurity incident Response Plan. This document will define how DC personnel will respond when/if a security incident occurs.

  • Flipped the spatial axes in the L1  DL-NIRSP  data generated by the current DL-NIRSP pipeline.  The DL team had indicated that the current 3D cubes were rotated by 90 degrees in the spatial dimensions.

  • Fixed the gain issues in the DL-NIRSP pipeline. Preliminary tests of real DL-NIRSP data indicated that the gain correction was not being correctly computed and applied. 

 

Related content