2024 August 26 - 30
DKIST General
Operational Status
DKIST is in week 4 of OCP 2.8.
DKIST weathered Hurricane Hone on 8/25 with no significant damage.
Events
The Cycle 3 Science Review Committee (SRC) met at NSO Boulder - 8/26-8/28.
Personnel
SciOps and OpsTools team
Accomplishments
Ongoing observing support for OCP2.8.
Preparing the tools and workplace for the Experiment Generation process.
Completed the science operations support schedule for OCP2.9 (resident scientist and science operations specialists shift schedules).
Completed the SOS group schedule to support the on-sun Instrumentation campaign in Nov-Dec.
TechOps team
Accomplishments
Ongoing TechOps support for OCP 2.8
Pau Hana -> Sebastien Goodbye, Linda Happy Retirement & Sarah Congrats on Tenure.
FAA Laydown -end of use and inspection confirmed with FAA Manager.
System inspection and recovery, mainly leaks internal from weather due to Hurricane Hone passing by.
Detailed planning and resource loading complete for engineering 2024D starting 9/9.
InstOps team
Accomplishments
Ongoing Instrumentation support for OCP 2.8
Planning completed for September engineering work.
Contract started for M9b construction.
Testing of DL-NIRSP and ViSP software during bad weather.
Data Center team
Accomplishments
ongoing ingestion and processing of data for OCP 2.8
Completed Cryo-NIRSP trial#8 and released the Cryo-NIRSP pipeline V1.0
Began processing the backlog of Cryo-NIRP data in DC stores. Currently at about 75% through the backlog. Estimated failure rate on pipeline runs is currently about 20-25%, mostly due to missing data or problems with correlations These will be triaged after the runs are completed
updated the quality report generation to allow 1D binning (a mode that DL-NIRSP uses) in PolCal metrics.
Refactored quality metrics code to speed it up. Current DL-NIRSP runs were taking an order of magnitude longer to run than previous instruments.